No time to waste! Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!

the opportunity

Puzzle was engaged to quickly develop and implement a relocation strategy to move a series of nursing, consultant and administrative departments across multiple buildings and sites to enable redevelopment construction.

 

This required an adaptive, agile approach as the requirements, move windows and operational readiness activities needed to dovetail with a constantly changing operational environment. Fit-out works were to be undertaken ahead and during each transition, meaning effective coordination between the fit-out contractor and Puzzle was vital and a scope of works, market review and recommendation to appoint a relocation vendor was also required.

 

Given the medical nature of the organisation, it was imperative that the hospital’s BAU operations were maintained during the moves.

our approach

Planning, planning, planning and yet more planning. With the tight timeframe and complex nature of the transition it was critical that the plan ensured moves went smoothly. Puzzle deployed our tried and trusted approach ensuring all factors were understood, working closely with the health and construction teams. We developed and iterated a comprehensive plan that included:

  • Detailed move sequence + daily run sheets, planned down to the work-point

  • Plans for 9 move phases, across 7 sites and 15 buildings

  • Integrating planned moves with the fit-out program

  • Providing guidance and support to the health team for move readiness information and activities

  • Developing a full scope of works, onboarding and close on-site coordination of the removalist team

  • Post move support and confirmation that all services were back online post move

the results

Approximately 900 staff and 30 departments were relocated over 4 weeks with daily changes accommodated.

 

This project was successfully managed by a multi-disciplinary Puzzle team across the country to enable key oversight, on the ground management and live re-planning in parallel.

 

Combining our extensive experience in critical operational environments, change management, public sector, human factors, and logistics allowed our team to delight the hospital project team and achieve:

  • No operational downtime

  • Accurate relocation of all assets and equipment

  • Completion of all moves to plan enabling redevelopment of the vacated buildings on schedule

blueprint

change

transition

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
leading financial institution - paperlite

Establishing a “new normal”, pioneering new ways of working, and building enthusiasm and positivity in the client’s team.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
local
government

The transformation of 6,195 square metres of council offices into an innovative, collaborative, flexible workplace​.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
public
hospital

No time to waste! Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
emergency
services

Puzzle were entrusted to manage the complex transition of a critical emergency services operation centre housing 600 staff.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
federal government department #1

Using an evidence-based approach to test and refine a novel real estate strategy…the introduction of satellite Hubs.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
state
government

We love a challenge...co-locate 2,800 staff from 10 sites (five departmental divisions and 10 agencies) to a new building...during a global pandemic.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
financial institution FWOW

Navigating a path towards a ‘new normal’, leveraging the lessons from the remote working experience and defining future ways of working.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
global law
firm

From negative to positive...how a change management program assisted to shift staff sentiment during a move to agile working.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
federal government department #2

Deploying new technology with a user-centred approach to drive high levels of engagement and adoption.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
global comms
group

Leveraging a co-location project to re-define culture and drive improved agility, collaboration and flexibility.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
national
broadcaster

The show must go on! Relocating three broadcast studios and 645 staff in an incredibly tight window between the evening newscast and the following days’ morning show.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
leading financial
institution

Using data and evidence as a basis to drive “right-sizing” in CRE decision making.

Plan and relocate 900 health staff between 15 buildings and across 7 sites within 3 months!
federal government department #3

Establishing a “new normal”, pioneering new ways of working, and building enthusiasm and positivity in the client’s team.